|
Lawrence
Barn
Historic Community Center
Volunteer Projects
A major
goal of the Lawrence Barn project was to give every person in the town
the opportunity to work on the barn or project is some way to allow them
to feel that it was indeed a “community” center. There were
many jobs to be done and the following is a list of some of the construction projects that
were done by volunteers.
Site
Plan & Survey Work:
This was contributed by Bob Cormier and Cuoco & Cormier.
Demolition
of the old building:
This work was done at reduced rates by Doug Orde and Hollis
Construction.
Excavation
and Foundation Work:
The majority of this work was contributed by Amos White and
Homes by Paradise.
Move
beams back to Hollis:
The restored beams were loaded in Berwick, Maine, by Arron Sturgis’
crew, and unloaded in Hollis under his supervision. Trucking was by Honi Glover, Balcomb Trucking, and by Law
Trucking. Crane work is being contributed by Herm Stickney and Pioneer
Tree.
Ship
Lap sheathing:
Arron’s crew did the roof. Volunteers
did all the walls. All the walls of the old barn
were sheathed prior to installation
of the SIPS panels. The
pine boards for both the interior ship lap sheathing and the exterior
board and battens were provided at below cost by Lorin Rydstrom
and Seaboard International.
SIP
Installation:
Mostly by the Panel Pro’s. Arron’s
crew was there to make the connections from the old frame to the new
SIPS.
Install
Windows and doors:
The windows and small doors were cut into the SIPS panel
and then flashed and trimmed using pine boards.
Exterior
Batten and Boards:
We used rough vertical pine boards that are 10” and 12”
wide. The 1x5 batten were nailed over the SIP panel (& TYVEC)
and then the pine board. The
walls are about 15 feet high. Care
was taken to keep them plumb and to finish neatly with large
boards at corners and doorways.
Frame
end of barn, bathroom shed and entry area:
Keith Adamyck of Adamyck Homes coordinated the
framing work. The
building materials for this and other areas of work were being provided
at cost by Jerry Eckman and Reeds Ferry Lumber.
Standing
Seam Metal Roofing:
The roofing labor was contributed by Jeff Taylor and Viking
Roofing. He also
provided the materials at cost.
Interior
Partitions:
After the concrete floor is poured these walls need to be framed to
allow electrical wiring to take place.
Plasterboard
Walls & Ceilings:
The sheetrock labor and materials were donated by David
McCartney and Gemini Construction.
Install
Kitchen:
The cabinets were donated by John Testa of Kitchen Concepts. Other members of the kitchen team are Denise April and Chuck
Mussin.
Exterior
Staining:
Cabot’s Stain company contributed the stain.
Roger Skillings and Skillings Well Company donated the labor
and materials for the pump and equipment necessary to develop the water
pressure on the site.
Plumbing:
Joe Cianci and J.J. Ciampa & Son provided the plumbing
materials and labor at reduced rate.
Electrical:
Paul Armstrong & Dunwell Electric provided the electrical
design, materials, and installation at discounted rates.
Audio
and Computer Wiring:
Jim Belanger & Beltronics donated this labor and material.
Heating
and AC:
David Brassard co-coordinated the heating system.
Landscaping:
Pat Coughlin and the Colonial Garden Club are organizing the landscape design
and materials, including walkways, small stone walls, and plantings.
|