Re-assembling

The Lawrence Barn Community Center has been reconstructed on Nichols Field in Hollis, NH, in the approximate location of the previous field house. 

Construction Plan
(Drawn by BMA of Amherst)

 

 

 
Plan Interior

Lawrence Barn
Historic Community Center
Volunteer Projects

A major goal of the Lawrence Barn project was to give every person in the town the opportunity to work on the barn or project is some way to allow them to feel that it was indeed a “community” center. There were many jobs to be done and the following is a list of some of the construction projects that were done by volunteers. 

Site Plan & Survey Work:
This was contributed by Bob Cormier and Cuoco & Cormier

Demolition of the old building:
This work was done at reduced rates by Doug Orde and Hollis Construction

Excavation and Foundation Work:
The majority of this work was contributed by Amos White and Homes by Paradise

Move beams back to Hollis:
The restored beams were loaded in Berwick, Maine, by Arron Sturgis’ crew, and unloaded in Hollis under his supervision. Trucking was by Honi Glover, Balcomb Trucking, and by Law Trucking. Crane work is being contributed by Herm Stickney and Pioneer Tree. 

Ship Lap sheathing:
Arron’s crew did the roof. Volunteers did all the walls. All the walls of the old barn were sheathed prior to installation of the SIPS panels. The pine boards for both the interior ship lap sheathing and the exterior board and battens were provided at below cost by Lorin Rydstrom and Seaboard International

SIP Installation:
Mostly by the Panel Pro’s.  Arron’s crew was there to make the connections from the old frame to the new SIPS. 

Install Windows and doors:
The windows and small doors were cut into the SIPS panel and then flashed and trimmed using pine boards. 

Exterior Batten and Boards:
We used rough vertical pine boards that are 10” and 12” wide. The 1x5 batten were nailed over the SIP panel (& TYVEC) and then the pine board. The walls are about 15 feet high. Care was taken to keep them plumb and to finish neatly with large boards at corners and doorways. 

Frame end of barn, bathroom shed and entry area:
Keith Adamyck of Adamyck Homes
coordinated the framing work. The building materials for this and other areas of work were being provided at cost by Jerry Eckman and Reeds Ferry Lumber. 

Standing Seam Metal Roofing:
The roofing labor was contributed by Jeff Taylor and Viking Roofing. He also provided the materials at cost.

Interior Partitions:
After the concrete floor is poured these walls need to be framed to allow electrical wiring to take place.

Plasterboard Walls & Ceilings:
The sheetrock labor and materials were donated by David McCartney and Gemini Construction.

Install Kitchen:
The cabinets were donated by John Testa of Kitchen Concepts. Other members of the kitchen team are Denise April and Chuck Mussin. 

Exterior Staining:
Cabot’s Stain company
contributed the stain.

 
Roger Skillings and Skillings Well Company
donated the labor and materials for the pump and equipment necessary to develop the water pressure on the site. 

Plumbing:
Joe Cianci and J.J. Ciampa & Son
provided the plumbing materials and labor at reduced rate. 

Electrical:
Paul Armstrong & Dunwell Electric
provided the electrical design, materials, and installation at discounted rates.

 Audio and Computer Wiring:
Jim Belanger & Beltronics
donated this labor and material.

 Heating and AC:
David Brassard
co-coordinated the heating system. 

Landscaping:
Pat Coughlin and the Colonial Garden Club
are organizing the landscape design and materials, including walkways, small stone walls, and plantings.